“Huge progress” achieved during rail closure

Rail track maintenance being carried out as part of the recent summer works programme by KiwiRail and Auckland Transport. Photos supplied

KiwiRail and Auckland Transport (AT) claim “huge progress” has been made across Auckland’s rail network during the extended summer closure.

“Passengers boarding trains in Auckland from today will enjoy improved reliability and a new direct connection to Pukekohe as part of the huge progress made,” they say.

The four-week closure allowed KiwiRail to “blitz” the network while trains weren’t running, keeping the programme on track for City Rail Link-readiness and the faster, more frequent services it will bring.

“This summer more than 1350 workers descended on the network across 110-plus sites, working 24/7 wherever possible,” says André Lovatt, chief infrastructure officer at KiwiRail.

“In many areas they were able to achieve more progress than planned.

“Having a full four weeks with no passenger trains and therefore no energised powerlines meant we were able to deliver a massive amount of work without having to fit around trains.

“We know it’s a big ask for passengers.

“We’re operating in a complex environment as we upgrade the network, integrating new systems with old, and sometimes this comes with teething issues, despite rigorous testing.

“But we hope the scale of what we’ve achieved will provide some confidence that it’s worth the inconvenience when so much progress has been made,” says Lovatt.

Works associated with installing a new pedestrian bridge at Middlemore Station.

KiwiRail and AT say a major highlight was opening the newly electrified 19 kilometres of rail line between Papakura and Pukekohe.

Electric passenger trains now run to Auckland’s city centre with no need to change trains at Papakura.

AT’s public transport and active modes director Stacey van der Putten thanks Aucklanders for their patience while the vital upgrade work took place and trains weren’t running.

“Although there was a comprehensive rail bus replacement service in place to keep people moving, I know it’s inconvenient for people not to be able to catch the train.

“All of the upgrades happening during closures will maximise the benefits of the City Rail Link when it opens in 2026, with faster journeys, trains up to every four-five minutes, better connections across Auckland and improved reliability,” says van der Putten.

“But from now rail customers will see some immediate improvements including electric trains from a new Pukekohe Station and safe new pedestrian access to Homai Station to replace level crossings.”

New sections of rail track being craned into position at Quay Park, Parnell, on the lines that travel to and from Britomart Station in downtown Auckland.

The summer rail works programme also delivered:

  • A total of 7.4km of rail reinstatement and 11.4km of drainage works completed for the Rail Network Rebuild in some of the network’s most difficult to access priority areas.
  • Stage 4 of the Rail Network Rebuild (between Papakura to Pukekohe) completed.
  • Full track laid with overhead line and signalling system testing completed for the Third Main Line between Puhinui and Otahuhu.
  • New safer pedestrian access at Homai Station to replace two level crossings.
  • Some 14.3km of rail “destressed” to minimise potential speed restrictions caused by temperature changes.
  • Some 13 turnouts replaced in total.
  • Some 3200 sleepers replaced across the network.
  • Some 19km of tamping – where a machine lifts the rail and compacts the ballast (rocks) underneath the sleepers.
  • Some 17.5km of rail “stabilised” – where a machine pressures and vibrates the ballast to lock everything into place, so it fits together like puzzle pieces.
  • Completion of a new pedestrian overbridge at Middlemore Station.
  • Some 22 storm recovery sites repaired across the network using 6500 tonnes of rock.
  • Overhead line modifications and continued civil and electrification installation activities for new Western power feed at Glen Eden.
Preparation works being undertaken by a KiwiRail crew for the delivery of new track entering the tunnel at Britomart.

KiwiRail and AT say this was the first in a series of closures for a final push to get the network ready for the City Rail Link.

The majority of the final stages of the Rail Network Rebuild will be delivered in extensions to the usual closures when all services are suspended during major holidays, they say.

“This allows teams to safely work on the tracks and inside tunnels. The next extended closure will be for 16 days around Easter 2025.”

They say the work programme is designed to condense network disruption into shorter, more intensive closures, leaving it fully operational for longer and at busier times.

For example, the network will be fully operational for more weekends this year, compared to 2024 and there’s a focus on keeping trains running for special events.

“We know it’s vital to get the most out of this time period,” says Lovatt.

“That’s why we’ll continue to work 24/7 wherever possible. Through the Rail Network Rebuild we’re achieving a decade’s worth of work over 14 months.

“Ultimately this will enable more efficient and faster train services.

“We thank commuters, passengers and freight customers for their patience with these disruptions as we safely deliver the huge amount of work,” says Lovatt.

A new train station at Paerata on the line between Papakura and Pukekohe is taking shape.
- Advertisement -Error, group does not exist! Check your syntax! (ID: 68)
- Advertisement -Error, group does not exist! Check your syntax! (ID: 70)
Error, group does not exist! Check your syntax! (ID: 69)
Error, group does not exist! Check your syntax! (ID: 72)

More from Times Online

- Advertisement -Error, group does not exist! Check your syntax! (ID: 69)

Latest

- Advertisement -Error, group does not exist! Check your syntax! (ID: 69)
- Advertisement -Error, group does not exist! Check your syntax! (ID: 76)