大梁就位东部公交大道如期开工

Progress to build stage 1 of the Eastern Busway is within budget and on schedule for completion in 2021. Work to build the new busway bridge reached a major milestone recently with the delivery of the beams that will span the length of the bridge.

Two beams are currently on-site, delivered independently by road from Whangarei. The delivery by truck was the largest ever single haul delivered from Northland.

These are the largest single steel beams ever to be fabricated in NZ.

The rollers required for the bridge to be launched into place are manufactured in Germany and weigh 6 tonnes each. There are currently 2 rollers on-site with 2 more to be delivered next week

The steel for the beams is manufactured in Korea, laboratory tested in both Korea and on arrival in New Zealand. The steel plate is cut and beams fabricated, painted and transported by Culham Engineering in Whangarei.

There are three main beams; The river edge beams are 66.5m each and the middle beam is 73.5 m.

Each beam weighs more than 100 tonne

Two piers are under constructed in the estuary. Each pier encompasses 8 foundation piles to hold the bridge. Each pile is 360 cubic meters of concrete poured in a single placement. The piers are formed by constructing a temporary steel boat weighing 75 Tonnes which is floated into position and lowered to bed of the estuary.

Each pier has 2 columns constructed on top, each 7 m in height.

Other key recent milestones in the project include the new layout of Panmure Roundabout into an intersection and laying the first concrete along sections of the new busway.

 

 

 

 

By clicking to accept for Times Online to be translated into Mandarin, you accept and acknowledge that it has been translated for your convenience using 3 rd party translation software. No automated translation is perfect, nor is it intended to replace human translators and are provided "as is." No warranty of any kind, either expressed or implied, is made as to the accuracy, reliability, or correctness of any translations made from English into Mandarin. Some content (such as images, videos etc.) may not be accurately translated due to the limitations of the translation software. The official text is the English version of the website. Any discrepancies or differences created in the translation are not binding and have no legal effect and should not be relied on by you for any decision-making purposes. If any questions arise related to the accuracy of the information contained in the translated website, refer to the English version of the website which is the official edited version.

点击同意将《时代在线》翻译成中文,即表示您接受并确认,该翻译是使用第三方软件为您方便起见而 提供的。请注意自动翻译并非完美无缺,也不旨在取代人工翻译,只能作为参考而已。对于英文到中文 的任何翻译的准确性、可靠性或正确性,我们不提供任何明示或暗示的保证。由于翻译软件的限制,某 些内容(如图片、视频等)可能无法准确翻译。   英文版本是本网站的官方正式文本。翻译中产生的任何差异或错误均不具有约束力,不具有法律效力, 您不应依赖由自动翻译软件生成的版本做出任何决策。如果对翻译后的网站中包含的信息的准确性有任 何疑问,请参阅本网站的官方编辑英文版本。

- 广告
- 广告

更多信息来自《泰晤士报在线

- 广告

最新

- 广告
- 广告