fbpx
星期六, 11 月 16, 2024

Improved Murphys Road now reopen to traffic

Auckland Transport (AT) transformed a section of the rural road, between Ormiston and Flat Bush roads, to one that can cope with the 15,600 vehicles using it each day. Times photo Wayne Martin

Murphys Road in Flat Bush has now reopened as a four-lane road following improvements.

Auckland Transport (AT) transformed a section of the rural road, between Ormiston and Flat Bush roads, to one that can cope with the 15,600 vehicles using it each day.

The project, which started in 2017, recognised Flat Bush as an area that will experience significant development in the coming years.

This growth needed to be supported by building or improving arterial roads, bus routes, pedestrian and cycling connection, AT said..

The $29.5 million project was built by Fulton Hogan.

Times photo Wayne Martin

Howick Local Board chair Adele White said she is thrilled to see Murphys Road open again.

“It is looking great and certainly provides easy access to the many new developments in the area.”

The work included building new walking and cycling facilities, to provide safe pedestrian access across Murphys Road.

“This project will improve daily life for residents in the Flat Bush and Ormiston area,” said David Nelson, AT’s Portfolio Delivery Director (Projects).

“The Murphys Road improvements will go a long way to support the significant development that we expect to see in the area.”

Earlier days in the project. Photo Auckland Transport

Improvement works to Murphys Road included:

  • Construction of a stream crossing to replace the existing culvert near Ormiston Road, which was built in 1966 and no longer met design standards.
  • Construction of a shared path along the entire length of Murphys Road.
  • New traffic signals at the intersection of Murphys Road and Kerrykeel Drive.
  • New signalised pedestrian and cycle crossing points north of Geranium Avenue.
  • New signalised pedestrian crossing south of Horsefields Drive.
  • A shared path on the south side of the culvert linking to the existing park cycleway.
  • Undergrounding of overhead services.
  • Landscaping and planting works.
  • Streetlight installation.

See more here.

By clicking to accept for Times Online to be translated into Mandarin, you accept and acknowledge that it has been translated for your convenience using 3 rd party translation software. No automated translation is perfect, nor is it intended to replace human translators and are provided "as is." No warranty of any kind, either expressed or implied, is made as to the accuracy, reliability, or correctness of any translations made from English into Mandarin. Some content (such as images, videos etc.) may not be accurately translated due to the limitations of the translation software. The official text is the English version of the website. Any discrepancies or differences created in the translation are not binding and have no legal effect and should not be relied on by you for any decision-making purposes. If any questions arise related to the accuracy of the information contained in the translated website, refer to the English version of the website which is the official edited version.

点击同意将《时代在线》翻译成中文,即表示您接受并确认,该翻译是使用第三方软件为您方便起见而 提供的。请注意自动翻译并非完美无缺,也不旨在取代人工翻译,只能作为参考而已。对于英文到中文 的任何翻译的准确性、可靠性或正确性,我们不提供任何明示或暗示的保证。由于翻译软件的限制,某 些内容(如图片、视频等)可能无法准确翻译。   英文版本是本网站的官方正式文本。翻译中产生的任何差异或错误均不具有约束力,不具有法律效力, 您不应依赖由自动翻译软件生成的版本做出任何决策。如果对翻译后的网站中包含的信息的准确性有任 何疑问,请参阅本网站的官方编辑英文版本。

- 广告
- 广告

更多信息来自《泰晤士报在线

- 广告

最新

- 广告
- 广告