Preparation for construction of AMETI Eastern Busway ramps up

The countdown to the second largest transport construction project in Auckland takes a major step forward next week with demolition due to start next week.

From Tuesday work will begin to remove 61 Auckland Council owned properties along the Panmure to Pakuranga stage of the AMETI Eastern Busway route.

The removal of properties on the northern side of Lagoon Drive and Pakuranga Road will finish by early 2019 to enable the main construction phase to start in March/April 2019.

The construction phase will take approximately two-years to widen parts of Lagoon Drive and Pakuranga Road  to create a dedicated, congestion-free busway, that will provide a similar style of service to the Northern Busway.

It will also involve transforming Panmure Roundabout into a safer signalised intersection, creation of new cycle and walking paths, improvements to public spaces and reserves, a second bridge across Tamaki River and several intersection upgrades.

When the $1.4b busway is fully operational, customers will be able to travel between Botany and Britomart, by bus and train, in less than 40 minutes.

Fencing has been installed around the first properties to be removed at the corner of Pakuranga Road and Ti Rakau Drive and security and safety measures have been put in place to secure the other properties while the demolition work progresses.

Auckland Transport and Panuku have been working closely with social and housing organisations to ensure a smooth transition for tenants of these properties and neighbouring residents, says Auckland Transport (AT) spokesperson Matt Poland.

The removal of properties may generate some noise and dust and allowances have been made with the contractor to minimise this as much as possible, he says.

AT Project Director, Duncan Humphrey says this work will significantly increase the visibly of the project for those who live, work and travel through this area

“While this progress is exciting and will result in vastly improved travel choices, journey times and reliability for East Aucklanders, we appreciate that there will be inconveniences and disruption caused by the removal of properties and imminent construction. We do have plans to minimise these impacts.”

This work coincides with public consultation activity for the Pakuranga to Botany stage of the project, including the Reeves Road Flyover , new station in Pakuranga and the continuation of the Eastern Busway and integrated cycling networks between Pakuranga Town Centre and Botany Town Centre.

Want to know more? 

An information drop-in centre has opened in Pakuranga Plaza.

People interested in finding out more about the property removal and construction for AMETI Eastern Busway can visit the information drop-in centre in Pakuranga Plaza between 2pm and 6pm on Tuesday or Thursday each week.

“Ensuring that we have accessible information about all aspects of the project is important. The drop-in centre is an opportunity for people to meet the team, find out more about the project and how it will benefit the wider East Auckland,” says Poland.

“It will also be a place to find out about the construction work between Panmure and Pakuranga.”

Countdown to construction:

  • Early 2018: Initial properties required are removed and archaeological investigations commence around the culturally significant Panmure headland (Mokoia Pa)
  • June 2018: Designation was approved for the next stage of AMETI Eastern Busway between Panmure and Pakuranga, which means the land required for the project has the approvals to proceed
  • August 2018: Tenders are sought for construction of Stage 1 between Panmure and Pakuranga
  • October 2018: Removal of remaining properties required for Stage 1 of AMETI Eastern Busway
  • March / April 2019: Main construction phase commences

Find out more about AMETI Eastern Busway at www.at.govt.nz/ameti

By clicking to accept for Times Online to be translated into Mandarin, you accept and acknowledge that it has been translated for your convenience using 3 rd party translation software. No automated translation is perfect, nor is it intended to replace human translators and are provided "as is." No warranty of any kind, either expressed or implied, is made as to the accuracy, reliability, or correctness of any translations made from English into Mandarin. Some content (such as images, videos etc.) may not be accurately translated due to the limitations of the translation software. The official text is the English version of the website. Any discrepancies or differences created in the translation are not binding and have no legal effect and should not be relied on by you for any decision-making purposes. If any questions arise related to the accuracy of the information contained in the translated website, refer to the English version of the website which is the official edited version.

点击同意将《时代在线》翻译成中文,即表示您接受并确认,该翻译是使用第三方软件为您方便起见而 提供的。请注意自动翻译并非完美无缺,也不旨在取代人工翻译,只能作为参考而已。对于英文到中文 的任何翻译的准确性、可靠性或正确性,我们不提供任何明示或暗示的保证。由于翻译软件的限制,某 些内容(如图片、视频等)可能无法准确翻译。   英文版本是本网站的官方正式文本。翻译中产生的任何差异或错误均不具有约束力,不具有法律效力, 您不应依赖由自动翻译软件生成的版本做出任何决策。如果对翻译后的网站中包含的信息的准确性有任 何疑问,请参阅本网站的官方编辑英文版本。

- 广告
- 广告

更多信息来自《泰晤士报在线

- 广告

最新

- 广告
- 广告